In short:
A major review into Australia's biggest renewable energy project has found it could cost up to $25 billion, which is about 12 times the original price.
uncertain
which → find → billion
Snowy 2.0 was initially set to cost $2b and come online in 2021.
asserted
Snowy → set → 2021
The project is now expected to be delivered in 2029.
asserted
project → expect → 2029
The cost of delivering Australia's biggest renewable energy project has doubled since the last estimate and is now set to become fully operational a year later than expected, according to a major review.
Snowy Hydro has released its much-anticipated cost reassessment for the Snowy 2.0 hydropower project, revealing it could cost up to $25 billion, with first power expected in early 2029 and the project to be fully operational later that year.
uncertain
project → deliver → 2029
While the Commonwealth-owned company has set a target cost of $22 billion, it is allowing for an additional $3 billion to be spent on the project if required.
asserted
billion → own → project
Snowy 2.0, which started being built seven years ago, had an initial budget of $2 billion and was originally expected to start operating in 2021.
asserted
which → start → 2021
Those figures were revised as part of a "project reset" three years ago, which projected first power would be delivered in late 2027 and Snowy 2.0 would be fully operational a year later, at a cost of $12 billion.
asserted
Snowy → revise → billion
Late last year it was announced that the project's contractor Future Generation Joint Venture (FGJV) would conduct a "line-by-line reassessment", which has now been released three months later than initially expected.
asserted
which → announce → reassessment
Snowy Hydro CEO Dennis Barnes said he was "incredibly disappointed" with the update.
"
asserted
he → say → update
We had a project that was stalled and had billions of dollars of claims on the table in 2023," he said.
uncertain
he → have → 2023
"I'm pleased we've got progress, progress doubled in the first year after the reset.
asserted
progress → get → reset
"What I'm disappointed about is obviously the resultant costs of the progress we're making."
asserted
we → make → progress
Mr Barnes said the "design immaturity" that was faced before the 2023 reset had contributed to the latest cost blowouts.
"We've understood that we're going to need a lot more people for a lot longer to deliver this job," he said.
asserted
he → say → job
"This job is 80 per cent people costs, we've got 5,000 people on the job now working across multiple work fronts and that's obviously a lot more than we thought in 2023."
The review found 65 per cent of machine tunnelling and 90 per cent of cavern excavation had now been completed and work to build the underground power station was underway.
asserted
work → get → station
While Mr Barnes said the project was in its "strongest position yet", he could not rule out further cost blowouts beyond the most recent targets.
"
uncertain
he → say → targets
There's never any guarantees with mega projects, we're doing a world first thing in many respects in really complex conditions," he said.
asserted
he → be → conditions
"But the project is hitting its milestones of late, we have a lot of the risks behind us.
asserted
we → hit → us
"
How did Snowy 2.0 get here?
asserted
Snowy → get → ?
Snowy 2.0 is designed to underpin Australia's electricity security and affordability over coming decades, as the country transitions away from fossil fuels.
asserted
country → design → fuels
Based in the New South Wales Snowy Mountains, it will link two dams through about 27 kilometres of tunnels and include an underground pumped hydro station the size of the Sydney Opera House.
asserted
it → base → House
The project will act like a giant battery, pumping water upstream when electricity is cheap and releasing it back downstream to generate power when demand is high.
asserted
demand → act → power
It has a total capacity of 2,200 MW and is expected to power three million homes for a week, the equivalent of about 26 million household batteries.
asserted
It → have → batteries
Unlike batteries, pumped hydro offers long-duration storage, meaning it is designed to be a renewable energy insurance policy during days when there is limited sun or wind.
asserted
it → pump → days
But Snowy 2.0 has been embroiled in controversy since it was announced by former Prime Minister Malcolm Turnbull in 2017, including cost blowouts, missed deadlines, scrutiny over safety issues and contractor disputes.
asserted
it → embroil → issues
A major setback came after one of the initial three tunnel boring machines, Florence, got stuck in early 2023 for 11 months after hitting soft ground and creating a sinkhole.
asserted
one → come → sinkhole
The National Audit Office gave Snowy 2.0 a glowing review in 2022 but the most recent audit, released earlier this year, found "significant deficiencies" in the management of the hydropower project.
asserted
audit → give → project
In a submission to a parliamentary inquiry examining the project's delivery, Snowy Hydro said initial "design immaturity" and the project's "inherent complexity" had been the primary drivers of additional costs.
asserted
immaturity → examine → costs
"Productivity underperformance and cost escalation have also been significant factors," the submission read.
asserted
submission → read → ?
"Others have related to project-specific complexities that have developed during delivery.
asserted
that → relate → delivery
Snowy Hydro has learned and taken action in response to these challenges."
asserted
Hydro → learn → challenges
A submission from Future Generation Joint Venture (FGJV), the group responsible for the project's construction, said "unprecedented geotechnical uncertainty" and "significant geopolitical upheaval" had contributed to cost escalations.
asserted
uncertainty → say → escalations
"Unlike metropolitan tunnelling projects, where initial ground investigations are typically well-developed, ground investigations within a national park are necessarily limited," the submission said.
asserted
submission → develop → park
"As a result, conditions only become fully apparent as excavation progresses."
Project benefits report released
Along with the cost reassessment, Snowy Hydro has also released an economic study conducted by engineering consultant GHD.
asserted
Hydro → become → GHD
It found the project will contribute $18 billion to Australia's economy during the delivery phase and reduce wholesale electricity costs by more than $7b by 2075.
asserted
project → find → 2075
Mr Barnes said all technologies were needed for the energy transition, including batteries, pumped hydro and gas for firming.
asserted
technologies → say → firming
"We issued a report earlier in the year to show what the grid looked like with and without Snowy 2.0 and on those periods, which are pretty common, where we get no wind and we get no sun for days on end, batteries run out of juice, they don't get recharged," he said.
"
asserted
he → issue → juice
We actually saw that in January in South Australia, there was a period where the batteries run out of juice and prices went very high.
asserted
prices → see → juice
"So with Snowy 2.0 in the grid, we see that the prices in those periods were $7,000 a MWh lower."
asserted
prices → see → periods
A joint statement from Energy Minister Chris Bowen and Finance Minister Katy Gallagher said abandoning the hydropower project would "undermine grid reliability", scrap 5,000 jobs and lead to higher electricity bills.
asserted
abandoning → say → bills
"Once completed, Snowy 2.0 will be an incredible national asset, supporting Australia's energy security, price stability and the transition to renewable energy," the statement said.
asserted
statement → complete → energy
…and 1 more, not listed.