Snowy 2.0 to cost 12 times more than initial budget with further delays

Read the original at ABC News (AU) ↗
Cite

Stephens, R. (2026, October 22). Snowy 2.0 to cost 12 times more than initial budget with further delays. ABC News (AU). https://www.abc.net.au/news/2026-10-22/cost-of-snowy-hydro-expansion-doubles/107276162

Dated from the outlet's own feed. Check the original for its byline.

ABC News (AU) · collected 2026-10-22 · by Romy Stephens

Quick Summary

The review into Australia’s Snowy 2.0 hydropower project reveals it could cost up to $25 billion, which is about 12 times its original budget of $2 billion set when construction began seven years ago. Initially expected to be operational by 2021 and later revised to late 2027, the first power from Snowy 2.0 is now anticipated in early 2029 with full operation planned for later that year. Dennis Barnes, CEO of Snowy Hydro, acknowledged the cost increase due to design challenges and staffing needs but emphasized that the project remains on track despite these setbacks.
Written locally by qwen2.5:14b on 2026-10-22, using this article's own text rather than the other coverage of the same event (that is the story summary below).

AI analysis runs on qwen2.5:14b, locally

Story summary

As of October 22, 2026, the cost of Snowy Hydro 2.0, Australia's largest renewable energy project, has skyrocketed to up to $25 billion, which is about 12 times its initial budget of $2 billion set in 2017 under the Turnbull government. The project, originally scheduled to start operations in 2021 and complete by late 2028 after a revision in 2023, now faces delays with full operation expected only by the end of 2029. Recent reviews reveal that machine tunnelling is 65% complete and cavern excavations are nearing completion, but construction involves approximately 5,000 workers, significantly more than initially anticipated. The Albanese government plans additional oversight and financing measures to support Snowy Hydro's current cost estimate of $22.2 billion, with a contingency for it to rise to $25 billion if necessary.

Written for “Snowy Hydro 2.0 Cost Overrun” on 2026-10-22, grounded in this article and the 1 other(s) covering the same event.
Why this leaning score
This article does not take a side on a contested political question, so it has no leaning score. That is an answer rather than a gap: a match report or a rescue can be warmly or critically written without being left or right, and scoring it anyway is how approval of a subject gets recorded as a political position.
No political leaning scored for article 98903 · logged 2026-10-22

Story

📰 Snowy Hydro 2.0 Cost Overrun
Economy/Business · 2 article(s) covering the same event. See how they differ ↓

Compared with similar articles

This article reads unscored and hedges 10% of its claims. Each row says how that neighbour differs.
The Guardian · 0.86 cosine similarity
⚖️ leaning not scored 🔴 7% hedged 2 of 28 📰 publisher trust 66
“Both articles report on the same major review of Snowy 2.0 project cost and timeline updates released on the same day, indicating the same specific incident.”
How this article was measured signals, leaning charts, publisher record, byline, topics and claims

Signals How these are calculated →

Claims extracted
41
sentences that state something as happening or true
Uncertain
10%
4 of 41 hedged ("reportedly", "may", "according to")
Leaning
not political
takes no side on a contested political question
Publisher signals
68/100
ABC News (AU)'s corrections and hedging, across everything collected from it. Not a measure of accuracy.
Outlets on this story
2
Economy/Business
Same framing elsewhere
1
articles that frame the event the way this one does
Analyzed 2026-10-22 · how these are computed

How this is being covered How these are calculated →

Article leaning vs. publisher reliability
Source leaning vs. consistency

Publisher

ABC News (AU) · 3688 article(s) · 9 correction(s) detected
Running correction rate · 9 correction(s)

Who wrote this

Romy Stephens
5 article(s) here · 1 carrying a prediction
🔮 In short: A major review into Australia's biggest renewable energy project has found it could cost up to $25 billion, which is about 12 times the original price.
🔮 There are concerns that unusually hot temperatures, combined with an increase in baseline warming due to climate change, could increase the risk of "flash droughts" this summer.
🔮 Climate diplomacy at the heart of security strategy Prime Minister Anthony Albanese will join global leaders at the pre-COP event which will feature preparatory talks ahead of next month's United Nations COP31 climate summit.
🔮 Lifting a ban on plug-in solar and batteries would unlock access to the technology for millions of apartment dwellers and renters for the first time. What's next?
🔮 Decades of research has deepened our understanding of how Pacific Ocean temperatures shape global weather, leaving countries better prepared than ever for potential impacts. But questions remain over how El Niño, and its cooler counterpart La Niña, will behave in a warming world. Fires linked to El Niño have blanketed Indonesia and Malaysia. 1983 El Niño record looms large In autumn 1982, weather conditions across eastern Australia shifted dramatically and rainfall effectively ceased.
2026-09-05 · assertive framing · Why this El Niño is different from all the others
Also by Romy Stephens
Nothing else under this byline is closely related to this article, so these are simply their most recent.

Topics

Australia Commonwealth Future Generation Joint Venture Snowy 2.0 Snowy Hydro

Subjects

Australia GPE · 3× Barnes PERSON · 2× Snowy Hydro ORG · 2× Commonwealth ORG · 1× Dennis Barnes PERSON · 1× FGJV ORG · 1× Future Generation Joint Venture ORG · 1× Malcolm Turnbull PERSON · 1×

Narrative

"This job is 80 per cent people costs, we've got 5,000 people on the job now working across multiple work fronts and that's obviously a lot more than we thought in 2023." The review found 65 per cent of machine tunnelling and 90 per cent of cavern excavation had now been completed and work to build the underground power station was underway.
framing: assertive · carried by 1 article(s) · first seen 2026-10-22
🔮 In short: A major review into Australia's biggest renewable energy project has found it could cost up to $25 billion, which is about 12 times the original price.
2026-10-22 · ABC News (AU)
Snowy 2.0 to cost 12 times more than initial budget with further delays · assertive framing

Claims (41 extracted, 4 hedged)

In short: A major review into Australia's biggest renewable energy project has found it could cost up to $25 billion, which is about 12 times the original price. uncertain
which → find → billion
Snowy 2.0 was initially set to cost $2b and come online in 2021. asserted
Snowy → set → 2021
The project is now expected to be delivered in 2029. asserted
project → expect → 2029
The cost of delivering Australia's biggest renewable energy project has doubled since the last estimate and is now set to become fully operational a year later than expected, according to a major review. Snowy Hydro has released its much-anticipated cost reassessment for the Snowy 2.0 hydropower project, revealing it could cost up to $25 billion, with first power expected in early 2029 and the project to be fully operational later that year. uncertain
project → deliver → 2029
While the Commonwealth-owned company has set a target cost of $22 billion, it is allowing for an additional $3 billion to be spent on the project if required. asserted
billion → own → project
Snowy 2.0, which started being built seven years ago, had an initial budget of $2 billion and was originally expected to start operating in 2021. asserted
which → start → 2021
Those figures were revised as part of a "project reset" three years ago, which projected first power would be delivered in late 2027 and Snowy 2.0 would be fully operational a year later, at a cost of $12 billion. asserted
Snowy → revise → billion
Late last year it was announced that the project's contractor Future Generation Joint Venture (FGJV) would conduct a "line-by-line reassessment", which has now been released three months later than initially expected. asserted
which → announce → reassessment
Snowy Hydro CEO Dennis Barnes said he was "incredibly disappointed" with the update. " asserted
he → say → update
We had a project that was stalled and had billions of dollars of claims on the table in 2023," he said. uncertain
he → have → 2023
"I'm pleased we've got progress, progress doubled in the first year after the reset. asserted
progress → get → reset
"What I'm disappointed about is obviously the resultant costs of the progress we're making." asserted
we → make → progress
Mr Barnes said the "design immaturity" that was faced before the 2023 reset had contributed to the latest cost blowouts. "We've understood that we're going to need a lot more people for a lot longer to deliver this job," he said. asserted
he → say → job
"This job is 80 per cent people costs, we've got 5,000 people on the job now working across multiple work fronts and that's obviously a lot more than we thought in 2023." The review found 65 per cent of machine tunnelling and 90 per cent of cavern excavation had now been completed and work to build the underground power station was underway. asserted
work → get → station
While Mr Barnes said the project was in its "strongest position yet", he could not rule out further cost blowouts beyond the most recent targets. " uncertain
he → say → targets
There's never any guarantees with mega projects, we're doing a world first thing in many respects in really complex conditions," he said. asserted
he → be → conditions
"But the project is hitting its milestones of late, we have a lot of the risks behind us. asserted
we → hit → us
" How did Snowy 2.0 get here? asserted
Snowy → get → ?
Snowy 2.0 is designed to underpin Australia's electricity security and affordability over coming decades, as the country transitions away from fossil fuels. asserted
country → design → fuels
Based in the New South Wales Snowy Mountains, it will link two dams through about 27 kilometres of tunnels and include an underground pumped hydro station the size of the Sydney Opera House. asserted
it → base → House
The project will act like a giant battery, pumping water upstream when electricity is cheap and releasing it back downstream to generate power when demand is high. asserted
demand → act → power
It has a total capacity of 2,200 MW and is expected to power three million homes for a week, the equivalent of about 26 million household batteries. asserted
It → have → batteries
Unlike batteries, pumped hydro offers long-duration storage, meaning it is designed to be a renewable energy insurance policy during days when there is limited sun or wind. asserted
it → pump → days
But Snowy 2.0 has been embroiled in controversy since it was announced by former Prime Minister Malcolm Turnbull in 2017, including cost blowouts, missed deadlines, scrutiny over safety issues and contractor disputes. asserted
it → embroil → issues
A major setback came after one of the initial three tunnel boring machines, Florence, got stuck in early 2023 for 11 months after hitting soft ground and creating a sinkhole. asserted
one → come → sinkhole
The National Audit Office gave Snowy 2.0 a glowing review in 2022 but the most recent audit, released earlier this year, found "significant deficiencies" in the management of the hydropower project. asserted
audit → give → project
In a submission to a parliamentary inquiry examining the project's delivery, Snowy Hydro said initial "design immaturity" and the project's "inherent complexity" had been the primary drivers of additional costs. asserted
immaturity → examine → costs
"Productivity underperformance and cost escalation have also been significant factors," the submission read. asserted
submission → read → ?
"Others have related to project-specific complexities that have developed during delivery. asserted
that → relate → delivery
Snowy Hydro has learned and taken action in response to these challenges." asserted
Hydro → learn → challenges
A submission from Future Generation Joint Venture (FGJV), the group responsible for the project's construction, said "unprecedented geotechnical uncertainty" and "significant geopolitical upheaval" had contributed to cost escalations. asserted
uncertainty → say → escalations
"Unlike metropolitan tunnelling projects, where initial ground investigations are typically well-developed, ground investigations within a national park are necessarily limited," the submission said. asserted
submission → develop → park
"As a result, conditions only become fully apparent as excavation progresses." Project benefits report released Along with the cost reassessment, Snowy Hydro has also released an economic study conducted by engineering consultant GHD. asserted
Hydro → become → GHD
It found the project will contribute $18 billion to Australia's economy during the delivery phase and reduce wholesale electricity costs by more than $7b by 2075. asserted
project → find → 2075
Mr Barnes said all technologies were needed for the energy transition, including batteries, pumped hydro and gas for firming. asserted
technologies → say → firming
"We issued a report earlier in the year to show what the grid looked like with and without Snowy 2.0 and on those periods, which are pretty common, where we get no wind and we get no sun for days on end, batteries run out of juice, they don't get recharged," he said. " asserted
he → issue → juice
We actually saw that in January in South Australia, there was a period where the batteries run out of juice and prices went very high. asserted
prices → see → juice
"So with Snowy 2.0 in the grid, we see that the prices in those periods were $7,000 a MWh lower." asserted
prices → see → periods
A joint statement from Energy Minister Chris Bowen and Finance Minister Katy Gallagher said abandoning the hydropower project would "undermine grid reliability", scrap 5,000 jobs and lead to higher electricity bills. asserted
abandoning → say → bills
"Once completed, Snowy 2.0 will be an incredible national asset, supporting Australia's energy security, price stability and the transition to renewable energy," the statement said. asserted
statement → complete → energy
…and 1 more, not listed.