"to:
- Prevent access to all damaged structures, temporary structures, and areas affected by the storm.
- Hire a licensed professional engineer to assess all structures, including seating areas, affected by the storm, identify unsafe areas and determine the measures to be taken to address those areas.
- Prepare a report by Sept. 8 identifying the damage, measures to be taken and a schedule for the work.
- Carry out the necessary repairs identified by the engineer.
- Submit another report by Sept. 11 confirming the status of the repairs to be taken and "whether the affected structures are safe and structurally adequate for their intended use and occupancy.""