The federal government is “not responsible” for power regulation and cannot regulate power usage by AI data centres, Artificial Intelligence Minister Evan Solomon told a Senate committee on Thursday.
asserted
Solomon → regulate → Thursday
Solomon spoke to the Senate Committee on Social Affairs, Science and Technology on Thursday, where he was asked about power usage by data centres in Canada.
asserted
he → speak → Canada
So, we can’t put federal obligations on the power regulation,” he said, adding that provinces like Saskatchewan and Nova Scotia are in the process of creating their own data centre laws.
asserted
provinces → put → laws
At the same time, however, both information technology and electricity grids are considered critical infrastructure by the federal government, giving Public Safety Canada the ability to “manage risks and reduce vulnerabilities,” according to the National Strategy for Critical Infrastructure.
uncertain
technology → consider → Infrastructure
Doubling the capacity of Canada’s energy grid was “absolutely critical” to rolling out Canada’s AI strategy, Solomon said.
asserted
Solomon → double → strategy
“We work very closely with best practices around the world to develop very high standards on water use, energy use, investment in the community, strategic importance, consultation, and most importantly, transparency on the promises so you can actually hold them to account,” he said.
asserted
he → work → account
The federal government’s recently released ‘Responsible Data Centre Development Principles’ require that companies building new data centre projects “do not shift electricity costs onto Canadians” and “minimize water use and environmental impacts.
asserted
companies → release → use
”
160 data centre proposals
Solomon was also asked how many data centres Canada was looking to build.
asserted
Canada → ask → centres
Get daily National news
“We received proposals for… over 160,” he said.
asserted
he → get → 160
While large data centre projects will require around 100 megawatts of power per building, there “may be some smaller ones” as well, he added.
uncertain
he → require → building
“We have MOUs with about four (data center companies) so far,” he said.
asserted
he → have → four
- 3 arrested after Toronto marketplace sellers targeted in violent robberies: police
asserted
sellers → arrest → robberies
Toronto Crime Stoppers pauses tips after cyber breach affects 176K submissions
-
asserted
breach → pause → submissions
Ottawa gives Stelco 15 days to reverse Hamilton layoffs or face lawsuit
Ottawa is “supporting the building of Canadian data that are Canadian-owned,”
asserted
that → give → data
Solomon said, however, some major projects in Canada are being helmed by U.S. tech giants.
asserted
projects → say → giants
A company pursuing a wind and hydrogen development in Nova Scotia says it has plans for a $10-billion AI data centre in Cape Breton that it describes as the largest private investment in provincial history.
asserted
it → pursue → history
EverWind Fuels announced last week that U.S. AI company Anthropic has signed a 20-year lease for a 18,600-square metre data centre in Point Tupper, N.S., that would draw 95 megawatts of electricity during its first phase.
asserted
that → announce → phase
The data centre is scheduled to come online late next year.
asserted
centre → schedule → ?
A 325-megawatt expansion is expected in mid-2028, which would bring the development’s total energy demand to 420 megawatts, the company said.
asserted
company → expect → megawatts
Nova Scotia Premier Tim Houston said the data centre project was a major vote of confidence in the rural area about 200 kilometres east of Halifax.
asserted
project → say → Halifax
He said Canada does not have enough secure data infrastructure to meet the requirements of its businesses, governments and health-care institutions.
asserted
Canada → say → businesses
Data centres are typically massive operations that require immense amounts of electricity to run and cool off computer servers.
asserted
that → require → servers
Water from nearby Landrie Lake will be used to cool the Point Tupper data centre’s servers, and the company stressed it will safeguard the water supply.
asserted
it → use → supply
EverWind said the cooling system will be closed-loop, similar to a car’s radiator, with cooling fluid recycled or disposed of off site, not in local waterways.
asserted
system → say → waterways
The system will use an average of 100,000 litres of water per day in the first phase, which EverWind said is about the same as a large shopping mall.
asserted
EverWind → use → mall
That will expand to an average draw of 500,000 litre per day when the expansion is complete, about one per cent of the lake’s safe daily yield of 34 million litres.
asserted
expansion → expand → litres