What began as a community protest in Melbourne’s inner west over enormous electricity poles being installed on narrow residential streets has now rocked the nation’s highest-profile data centre developer, as it scrambles to find a new way to supply energy to its flagship centre.
asserted
it → begin → centre
On Wednesday, ASX-listed NextDC told investors it would slash its expected profits and construction spending as it dealt with delays in supplying energy to its M3 centre in West Footscray, triggering a share price plummet.
asserted
it → list → plummet
NextDC came out of a two-day trading halt on Wednesday warning investors that the final stages of the politically contentious development would also not be approved until after next month’s state election.
asserted
stages → come → election
The delays are the result of a community blockade in September, revealed by this masthead, against electricity distributor Jemena’s rollout of 15-metre tall 66,000-volt residential power poles.
asserted
delays → reveal → poles
The protests prompted Jemena to halt construction until at least February.
asserted
protests → prompt → February
The delays have left NextDC saying it now lacks the extra grid capacity needed to power its expanding data halls at West Footscray.
asserted
it → leave → Footscray
The market reaction against the data centre developer was sharp: NextDC shares collapsed to $5.46 on Wednesday, down more than 40 per cent from their Monday closing price of $9.57.
asserted
shares → collapse → 9.57
The crash wiped billions off the company’s valuation, driving its stock to its lowest point since 2019 – a far cry from its peak of $17.22 a year ago.
asserted
crash → wipe → 17.22
NextDC on Wednesday also revealed it was putting the brakes on its wider construction pipeline, in a move which could alarm state and federal governments as data centre construction is one of the few bright spots in the sluggish Australian economy.
uncertain
construction → reveal → economy
NextDC slashed its construction budget for the coming financial year from up to $5.75 billion to between $4.5 billion and $5 billion, pausing developments without client contract commitments.
asserted
NextDC → slash → commitments
Previously, the company had built new data centres without having tenants contracted to go into them.
asserted
tenants → build → them
NextDC chief executive Craig Scroggie said the company had paused expectations from its West Footscray project, and would halt speculative expansion projects and land buys not already locked in by paying clients.
asserted
company → say → clients
“With [West Footscray] revenue deferred, we have paused projects not backed by customer contracts and put that capital behind the capacity our customers have already contracted,” he said.
asserted
he → defer → capacity
Yarraville resident Milco Bogoevski was among those who led the community protest to stop Jemena installing its enormous power poles in his residential street.
asserted
Jemena → lead → street
He said while he was sympathetic to data centre operators – “No one here wants to see industry fail; we want industry to succeed” – what had happened was the direct result of power companies and business not listening to the community.
“These power lines, this material, it was going to be in our street, we were going to have to deal with it for decades after they left – power operators like Jemena, and [businesses like NextDC], they’re going to need to engage more with the community.”
asserted
they → say → community
Bogoevski said the community opposition to the enormous West Footscray data centre and the impact of other data centres in Melbourne’s inner west could help swing seats in the November 28 election.
uncertain
opposition → say → election
“The state government is responsible for power – it comes down to them.
asserted
it → come → them
There is a good chance that an issue like this could flip this seat away from Labor; we’ve got a couple of issues like this that Labor hasn’t paid attention to,” he said.
uncertain
he → be → attention
NextDC’s market shock represents the clearest evidence yet that Victoria’s rapid push to attract power-hungry artificial intelligence infrastructure has run into severe grid constraints and suburban backlash.
asserted
push → represent → constraints
The M3 facility in West Footscray is designed to eventually span 10 hectares in an industrial pocket adjacent to residential homes.
asserted
facility → design → homes
The site already occupies five hectares and was undergoing a $750 million expansion.
asserted
site → occupy → expansion
However, feeding the expanding site required Jemena to replace standard wooden electricity poles with 15-metre concrete poles carrying 66,000 volts along residential streets in West Footscray and neighbouring Yarraville.
asserted
feeding → feed → Footscray
A typical residential power pole carries about 400 volts.
asserted
pole → carry → volts
A Maribyrnong City Council spokeswoman noted that some poles in the rollout rise as high as 22 metres, which is equivalent to seven storeys.
asserted
which → note → storeys
The rollout ground to a halt in Yarraville last month following direct action by residents, who blockaded contractor trucks with parked cars, ignored door-knocks and filled excavation pits to stop high-voltage lines reaching the NextDC site.
asserted
lines → grind → site
Jemena bowed to pressure and paused work to consult further, leaving the high-capacity route unfinished.
asserted
Jemena → bow → route
NextDC said a state a planning permit decision for its next stages of its West Footscray project had also been delayed.
asserted
decision → say → project
With the Victorian government entering caretaker mode on November 3 ahead of the election, a planning decision for the site is now not expected until 2027.
asserted
decision → enter → 2027
The mounting political and community friction creates a growing challenge for the election.
asserted
friction → mount → election
As premier, Jacinta Allan and her then-economic development minister Danny Pearson aggressively courted hyperscale data operators, using fast-tracked planning schemes to bypass municipal councils and grant approvals in as little as 28 days.
asserted
Allan → court → days
Data centres consume about 2 per cent of national grid power, but the Australian Energy Market Operator has forecast that share could rise to 9 per cent by 2035 as AI adoption accelerates.
uncertain
adoption → consume → 2035
To address growing concerns, Premier Ben Carroll last month introduced new rules requiring data centre developers to supply their own renewable energy, use recycled water, and maintain a minimum 150-metre buffer from homes.
asserted
Carroll → address → homes
Community pushback is now hitting projects nationwide.
asserted
pushback → hit → projects
Developer Green Square was recently forced to pull a proposed project in Western Australia, Goodman Group shelved a $1.2 billion facility in the Sydney suburb of Lane Cove, and private developer Firmus was forced to abandon a planned $44 billion stock market float.
asserted
Firmus → force → float