In short:
The Independent Planning Commission (IPC) held a three-day hearing into a proposed silver and lead mine near Mudgee this week.
asserted
Commission → hold → Mudgee
A minerals expert told the IPC the nearby Lue Public School should be moved if the project was approved.
asserted
project → tell → IPC
The IPC is expected to hand down a determination by December 9.
asserted
IPC → expect → December
The NSW Independent Planning Commission (IPC) has been told a public school should be moved if a proposed silver and lead mine is approved, amid fears it could poison children.
uncertain
it → tell → children
The IPC heard three days of evidence this week in Mudgee as it reassessed a proposal to extract 30 million tonnes of silver, lead and zinc over 23 years near Lue.
asserted
it → hear → Lue
The project has divided the community, with advocates touting the economic benefits and others raising concerns about potential environmental and health impacts.
asserted
others → divide → impacts
Proponent Silver Mines Limited's managing director Jo Battershill implored the panel to approve the development.
asserted
director → implore → development
"The project would provide investment and economic diversification for the mid-western region," he said.
asserted
he → provide → region
Almost 100 people spoke at the hearing, with the majority opposed to the mine.
asserted
majority → speak → mine
Only a few who spoke in support were not employees.
asserted
who → speak → support
On Wednesday, a group of farmers rode tractors and utes from Lue into Mudgee as part of their protest action.
asserted
group → ride → action
Along with dozens of local residents, experts from around Australia also addressed the hearing.
asserted
experts → address → hearing
He told the hearing he believed the project's potential for lead exposure posed an unacceptable risk to children at Lue Public School, located two kilometres from the mine site.
asserted
potential → tell → site
"I recommend that the Lue school, being at the boundary of dust deposition of [the] Bowdens mining project, be moved," Professor Noller said.
asserted
Noller → recommend → project
"The management plan would be underestimating the true quantity of deposited lead that is relevant in terms of assessing the risk to adults and particularly children."
asserted
that → underestimate → adults
Mr Battershill told the IPC that while the concern was understandable, the project had undergone extensive independent review.
asserted
project → tell → review
"Predicted health risks from the project, including from lead, are very low and are not expected to result in adverse human health impacts," he said.
asserted
he → predict → impacts
"It has been carefully assessed, and multiple layers of monitoring and management would apply throughout the life of the project.
asserted
layers → assess → project
"
Lead exposure
Mudgee-based general practitioner Peter Bryant told the panel dust from the project would threaten residents across the district.
asserted
dust → base → district
"There are no levels of lead exposure which are known to be without risk of harm," Dr Bryant said.
asserted
Bryant → be → harm
"I don't want to find myself frequently requesting blood tests for children who live in this area to check their lead levels.
asserted
who → want → levels
"I really hope not to be talking with parents about the high levels of lead that have been found in their child's blood and discussing the long-term implications this could have on their blood development and ongoing health.
uncertain
this → hope → development
Water concerns
As part of the proposal, Silver Mines Limited would use approximately 2,000 megalitres of water a year for processing and dust suppression.
asserted
Limited → use → processing
Mr Battershill said assessments found average water supply reliability to be approximately 99.4 per cent.
asserted
reliability → say → ?
"The water balance monitoring found that except during extreme drought conditions, sufficient water would be available to meet operational demands," he said.
asserted
he → find → demands
Martin Krogh worked for the NSW government as a scientist for more than 30 years, including at the former Sydney Catchment Authority.
asserted
Krogh → work → Authority
"In my view, there are significant shortcomings in the Bowdens Environmental Impact Statement surface water assessment," he told the panel.
asserted
he → be → panel
"During drought conditions and very dry years, it appears highly unlikely there will be sufficient water falling in the catchment to support the environment, basic stock and domestic use, and downstream irrigation.
asserted
it → appear → environment
The project was previously green-lit by the IPC in 2023, however a legal challenge by a local landcare group in the NSW Court of Appeal saw its approval overturned.
asserted
approval → light → Appeal
The Court of Appeal found the impact of a 13km transmission line had not been properly assessed and thus declared the development "null and void".
asserted
development → find → line
The IPC is due to hand down its determination on the project by December 9.
asserted
IPC → hand → December