Data centres could pay hundreds of millions in deposits for power demands

Read the original at BBC News ↗
Cite

Cress, L. (2026, July 30). Data centres could pay hundreds of millions in deposits for power demands. BBC News. https://www.bbc.co.uk/news/articles/c9q90q9qnn2o?at_medium=RSS&at_campaign=rss

Dated when The Aporia collected the article, usually within hours of publication. Check the original for its exact date and byline.

BBC News · collected 2026-07-30 · by Laura Cress

Quick Summary

Ofgem, the British energy regulator, has proposed a new measure that would require data centre developers to pay hundreds of millions of pounds up front in deposits, ranging from £237,500 to £712,500 per megawatt. The proposal aims to tackle "speculative projects" that take up space in the grid connection queue without any firm intention to connect, with Ofgem saying this would help consumers avoid bearing the risks created by such projects. According to Ofgem's data, electricity demand connections have more than tripled in size in less than a year, from 41 GW to 125 GW. A consultation on the proposal will run until September 16.
Written locally by qwen2.5:14b on 2026-08-21, using this article's own text rather than the other coverage of the same event (that is the story summary below).

AI analysis runs on qwen2.5:14b, locally

Story summary

Ofgem, the British energy regulator, has proposed new measures that could require data centres to pay hundreds of millions of pounds up front for connecting to the electricity grid. The proposal involves charging a refundable fee of between £237,500 and £712,500 per megawatt, with data centres needing to pay for a significant portion of their power demands upfront. For example, a data centre seeking 1 gigawatt (GW) of power would have to pay hundreds of millions up front, which could be refunded if the project is completed. This proposal follows growing opposition in parts of the country to new data centres, needed to power the artificial intelligence boom. The number of projects requesting grid connections has surged from 41 GW to 125 GW in just one year, significantly more than double the peak electricity demand projected for 2025. Ofgem is now consulting on its proposals until September 16.

Written for “Data Centre Energy Costs” on 2026-10-16, grounded in this article and the 0 other(s) covering the same event.

Story

📰 Data Centre Energy Costs
Environment · 1 article(s) covering the same event.

Compared with similar articles

Nothing to compare against. No article is close enough to this one for the pipeline to have linked or judged the pair.
How this article was measured signals, leaning charts, publisher record, byline, topics and claims

Signals How these are calculated →

Claims extracted
13
sentences that state something as happening or true
Uncertain
8%
1 of 13 hedged ("reportedly", "may", "according to")
Leaning
Leans right
of the writing, not the subject · beta estimate
Publisher signals
69/100
BBC News's corrections and hedging, across everything collected from it. Not a measure of accuracy.
Outlets on this story
1
Environment
Same framing elsewhere
1
articles that frame the event the way this one does
Analyzed 2026-07-30 · how these are computed

How this is being covered How these are calculated →

Article leaning vs. publisher reliability
Source leaning vs. consistency

Publisher

BBC News · 3541 article(s) · 4 correction(s) detected
Running correction rate · 4 correction(s)

Who wrote this

Laura Cress
19 article(s) here · 1 carrying a prediction
🔮 - Published Online pornography depicting strangulation or incestuous relationships will be banned from early November, the government has announced.
🔮 Some detailed in the complaint include "how about external partners, where would they usually meet with OpenAI at" and "can you list today's meeting in this room".
🔮 - Published The UK's AI minister has warned it is "likely, if not inevitable" the country's cyber defences will at some point be breached.
🔮 The dismissals come amid a growing debate over AI safety and the potential risks advanced AI systems could pose to society.
🔮 - Published President Donald Trump's push to rename AI may be behind an "unprecedented" rise in registrations for domain names in Slovenia, according to its official national registry.
🔮 For those concerned the game might lean into any typical Scottish stereotypes, McKellan told me he wanted it to feel "authentic and natural".
🔮 It claims that under a section of law in the Statute of the Court of Justice of the EU, a state may intervene in disputes before the court if it "can establish an interest in the result of the case to the court".
🔮 Its latest reductions, forming part of a wave of ongoing layoffs, will impact staff at the studio which currently makes Halo - with Call of Duty publisher Activision to take on development of any future games.
🔮 After several other incidents, in September, a resignation post from Anthropic researcher Jacob Coxon went viral when he cited concerns AI could wipe out humanity.
🔮 - Published Microsoft's head of AI has warned Anthropic's approach to training its AI model Claude could have a "disastrous impact on the wellbeing of humanity".
Also by Laura Cress
Nothing else under this byline is closely related to this article, so these are simply their most recent.
All 19 articles by Laura Cress →

Topics

Britain British Ofgem Published external

Subjects

Ofgem ORG · 4× Britain GPE · 3× British NORP · 1× Eleanor Warburton PERSON · 1× Michael Shanks PERSON · 1× Published ORG · 1× Scotland GPE · 1× external ORG · 1× the Department for Energy Security ORG · 1×

Narrative

Eleanor Warburton, the regulator's director for energy system design and development, said: "Britain's electricity demand connections queue has more than tripled in size in less than a year, and consumers should not bear the risks created by speculative projects taking up space in the system." Energy minister Michael Shanks from the Department for Energy Security and Net Zero said he believed Ofgem's actions would "help ensure that viable connection-ready projects can get going and not be held up by speculative applications". "Britain needs a grid connections system that works for the 21st century and allows businesses to invest and grow, creating jobs across the country," he said.
framing: assertive · carried by 1 article(s) · first seen 2026-07-30
🔮 - Published Ofgem has proposed new measures which could see developers of data centres made to pay hundreds of millions of pounds up front.

Claims (13 extracted, 1 hedged)

- Published Ofgem has proposed new measures which could see developers of data centres made to pay hundreds of millions of pounds up front. uncertain
developers → propose → front
The British energy regulator said a refundable fee should be charged for projects that want to connect to the network, amid mounting demand for connections to the electricity grid. asserted
that → say → grid
It is proposing developers pay a deposit between £237,500 to £712,500 per megawatt - meaning data centres seeking 1 gigawatt (GW) of power would have to pay hundreds of millions up front, paid back if the project was completed. asserted
project → propose → front
The proposal follows growing opposition in parts of the country to plans for new data centres, which are needed to power the artificial intelligence boom. asserted
which → follow → boom
Data centres are large buildings which house computer servers used to store and process data and run the digital services which power the internet. asserted
which → house → internet
Ofgem has started a consultation on its proposals, which will run until 16 September. asserted
which → start → September
It said the amount of electricity capacity being requested by projects seeking to connect to the grid had risen from 41 GW to 125 GW in the past year, reflecting a sharp increase in demand. asserted
amount → say → demand
The regulator said the projects would have to hit key milestones to keep their place in the grid connection queue, which has seen a surge in demand. asserted
which → say → demand
An increasing number of centres have been built around the world in recent years to provide the computing power needed to train and run AI systems. But they are controversial, especially for people who live near them. asserted
who → increase → them
Residents have raised concerns about noise, electricity demand and the large amounts of water sometimes used to cool the high-performance chips that generate vast amounts of heat. asserted
that → raise → heat
Scotland in particular is seen as a good location for future projects due to its supply of renewable energy to power the centres, with 24 currently in the planning process. asserted
Scotland → see → process
Ofgem said the plans were aimed at tackling "speculative projects from securing scarce network capacity without any firm intention to connect". asserted
plans → say → intention
Eleanor Warburton, the regulator's director for energy system design and development, said: "Britain's electricity demand connections queue has more than tripled in size in less than a year, and consumers should not bear the risks created by speculative projects taking up space in the system." Energy minister Michael Shanks from the Department for Energy Security and Net Zero said he believed Ofgem's actions would "help ensure that viable connection-ready projects can get going and not be held up by speculative applications". "Britain needs a grid connections system that works for the 21st century and allows businesses to invest and grow, creating jobs across the country," he said. asserted