In short:
East coast residents say St Marys Pass needs urgent upgrades or re-routing as large trucks and rockfalls pose risks to motorists.
asserted
trucks → say → motorists
The Tasmanian government recently released a report assessing seven options for the road, the most expensive costing up to $2.7 billion.
asserted
expensive → release → billion
The state and federal governments haven't yet committed to funding any full project and they're arguing about what a funding split might look like.
uncertain
split → commit → what
A Tasmanian east coast resident is concerned she could "become a statistic" if changes aren't made to St Marys Pass — a notorious stretch of road frequently used to get to the coast.
uncertain
changes → concern → coast
The winding, six-kilometre stretch of convict-built road, connecting the town of St Marys with the east coast struggles to cater for modern traffic.
asserted
stretch → build → traffic
Scamander resident and former Burnie mayor Sandra French has lived in the coastal town for eight years and often uses St Marys Pass to get to Launceston.
asserted
French → live → Launceston
"The trucks are getting bigger, they're getting heavier and we're having falls, landslides coming from the top," she said.
asserted
she → get → top
"I went up one day and it was falling behind me and I rang police and they had to come down and clear it."
Ms French also recalled a trip where she was nearly hit by a truck coming through.
asserted
she → go → truck
"This huge truck came round … and he came so close to the car I pulled over and put my hands over my face thinking, 'he's going to hit me',"she said.
asserted
he → come → face
"Thankfully he didn't … it was just unbelievable."
asserted
it → do → ?
Ms French said she would like a route just for heavy vehicles.
asserted
she → say → vehicles
"These trucks are on secondary roads, that were built for oxen and a cart."
asserted
that → build → oxen
St Marys resident Carmel Sullivan said she also felt scared using the road.
asserted
she → say → road
"I suffered a bit of whiplash when I was young in a car accident and now I tense up doing St Marys Pass,"she said.
asserted
I → suffer → accident
Ms Sullivan said she did not know anyone who liked using the road.
asserted
who → say → road
"Every single mainland visitor I've had, have said what a terrible road that is," she said.
asserted
she → have → ?
Seven options considered
Both women and most others in the surrounding communities want a safer drive.
asserted
women → consider → drive
Some want a completely new route, others an upgrade of the current infrastructure.
asserted
others → want → infrastructure
Earlier this month Building Tasmania released a report detailing costings and community feedback on seven proposals to improve the notorious road.
asserted
Tasmania → release → road
Project costs ranged from $50 million to $2.7 billion.
asserted
costs → range → billion
An option known as the "blue route", which would re-route the pass along an existing TasNetworks power line north of the current road, received the most positive community response.
asserted
which → know → response
Building Tasmania also favoured it as the "shortest and straightest route" but when factoring in cost, community support and deliverability, it backed what is known as the "purple route".
asserted
what → favour → route
"The purple route provides the best balance of cost, deliverability, environmental outcomes and community support,"the report said.
asserted
report → provide → cost
The cheapest option at $50-$70 million, the purple route would maintain and upgrade the existing route over 10 years.
Challenging terrain
For three months in late 2022, the narrow stretch of road, sandwiched between forest and large rock walls, was closed after a major landslip.
asserted
stretch → maintain → landslip
The closure, between the Tasman Highway and Esk Highway, significantly affected emergency service access, the delivery of essential goods and tourism during the sector's peak period.
asserted
closure → affect → period
The steep slopes, geology, and sensitive ecosystems across the region create "significant challenges" for road design and construction for both new and existing roads, according to Building Tasmania.
uncertain
slopes → create → Tasmania
A spokesperson said most upgrade options assessed had sections of more than 50 per cent that would be highly susceptible to landslip.
asserted
that → say → landslip
The "red route", which would use an existing road through Upper Scamander, was the exception with 25 per cent of the route susceptible.
asserted
cent → use → route
That option was costed at $2.7 billion.
asserted
option → cost → billion
Who will pay?
asserted
Who → pay → ?
State Infrastructure Minister Kerry Vincent has all but ruled out the two options costed at $1 billion and $2.7 billion.
asserted
Vincent → rule → billion
"[That] is a phenomenal amount of money when we've got an existing road there that can be done up much cheaper," Mr Vincent said.
"
asserted
Vincent → get → road
Alterations to the existing road are the most sensible.
asserted
Alterations → exist → road
"
But, even that cheapest option is not guaranteed of receiving funding.
asserted
option → guarantee → funding
"The recently released options assessment will be used to determine whether any of the options will progress to further planning and design work, noting any new routes will be extremely expensive to deliver," Mr Vincent said.
asserted
Vincent → release → work
Traditionally, road projects in Tasmania have been 80 per cent funded by the federal government and 20 per cent by the state government.
asserted
cent → fund → government
But the federal government's policy changed in late 2023 to preference for a 50:50 funding split.
asserted
policy → change → split
The federal government has allocated $10 million towards St Marys Pass upgrades.
asserted
government → allocate → upgrades
It is not yet clear if, or how, a complete project would be funded.
asserted
project → fund → ?
"The most cost-effective option to deliver immediate improvements is to upgrade portions of the existing road, and we are working with the Australian Government on the best use of their committed $10 million,"Mr Vincent said.
asserted
Vincent → deliver → 10
…and 9 more, not listed.