Capital Development Authority plans to execute 11th Avenue project in two phases

Read the original at Dawn ↗
Dawn · collected 2026-10-09 · by Kashif Abbasi

Quick Summary

The Capital Development Authority (CDA) plans to execute the 11th Avenue project in Islamabad in two phases. The first phase will cover a 3.5-kilometer stretch from E-11 interchange to Srinagar Highway, including an interchange at Srinagar Highway and is estimated to cost around Rs11 to 12 billion. CDA’s Directorate of Works Planning (DWP) recently approved the preliminary cost estimate (PC-I) worth Rs24.5 billion for the entire highway project from Margalla Avenue to IJP Road, which will span 7.5 kilometers with three lanes on each side and include around 17 bridges and overpasses. The project is expected to begin within two months as pre-tendering processes are underway.
Written locally by qwen2.5:14b on 2026-10-09, using this article's own text rather than the other coverage of the same event (that is the story summary below).

AI analysis runs on qwen2.5:14b, locally

Story summary

The Capital Development Authority (CDA) in Islamabad is planning to execute the 11th Avenue project in two phases. Initially, the project was scheduled for completion by December 2024 but received no funding from the federal government in the 2024-25 and 2025-26 budgets. The first phase will construct a 3.5km road from E-11 interchange to Srinagar Highway, including an interchange at Srinagar Highway. The entire 7.5km project includes around 17 bridges and overpasses, with three lanes on each side of the highway. CDA's Development Works Planning (DWP) recently approved a Project Cost Imprest (PC-I) worth Rs24.5 billion for the construction from Margalla Avenue to IJP Road. The engineering wing expects the entire project to be completed within one year once it starts formally in about two months after pre-tendering processes are finalized.

Written for “Islamabad City Development_Project” on 2026-10-09, grounded in this article and the 0 other(s) covering the same event.

Signals How these are calculated →

Claims extracted
24
claim-shaped sentences
Uncertain
17%
4 of 24 hedged
Leaning
not political
takes no side on a contested political question
Correction & hedging signals
71.2
corrections and hedging in what we collected; not a measure of accuracy
Outlets on this story
1
Politics
Narrative spread
1
articles carrying this framing
Analyzed 2026-10-09 · how these are computed

Story

📰 Islamabad City Development_Project
Politics · 1 article(s) covering the same event.

How this is being covered How these are calculated →

Article leaning vs. publisher reliability
Source leaning vs. consistency

Compared with similar articles

Nothing to compare against. No article is close enough to this one for the pipeline to have linked or judged the pair.

Publisher

Dawn · 1366 article(s) · 3 correction(s) detected
Running correction rate · 3 correction(s)
2026-10-07
POLICY: THE ISLAMIC DEBATE OVER CRYPTO
2026-10-01
Tennessee woman in hospital after execution 'failed': lawyers
2026-09-20
An eye on Balochistan border

Who wrote this

Kashif Abbasi
6 article(s) here · 1 carrying a prediction
🔮 According to the PC-I, the 7.5km road, with three lanes on each side, will be completed within a year.
🔮 We will challenge this action before available forums including courts,” he said.
🔮 The development came two days after Wani had told Dawn that Pakistan’s proposed tour to India was subject to government clearance and that the PHF would abide by whatever decision the government took.
🔮 Lawmakers express concern over growing menace of narcotics in educational institutions In May this year, the government had ordered a probe into the alleged leakage of Cambridge examination papers, directing NCCIA to investigate in coordination with Cambridge Assessment International Education (CAIE) amid concerns raised by parents and students over the alleged leakage of some papers.
🔮 Pakistan’s proposed tour to India for next month’s Asian Champions Trophy hockey tournament is subject to government clearance, the president of the country’s hockey federation Mohyuddin Ahmed Wani said on Monday, after Indian Punjab Chief Minister Bhagwant Mann claimed that Pakistan would participate in the event.
🔮 The Inter Board Coordination Commission (IBCC) on Saturday decided that Science Group equivalence would be awarded to students of foreign boards who had passed at least two science subjects, providing greater flexibility in academic pathways.
Also by Kashif Abbasi
Nothing else under this byline is closely related to this article, so these are simply their most recent.
All 6 articles by Kashif Abbasi →

Topics

CDA DWP ISLAMABAD PC-I The Capital Development Authority

Subjects

CDA ORG · 8× DWP ORG · 2× Dawn ORG · 2× ISLAMABAD GPE · 1× Shehbaz Sharif PERSON · 1× The Capital Development Authority ORG · 1×

Narrative

They said that under the original plan, the project should have been completed by December 2024, but the federal government did not allocate any funds for the public welfare project in its 2024-25 and 2025-26 budgets.
framing: assertive · carried by 1 article(s) · first seen 2026-10-09
🔮 According to the PC-I, the 7.5km road, with three lanes on each side, will be completed within a year.

Claims (24 extracted, 4 hedged)

The Capital Development Authority (CDA) is planning to execute the 11th Avenue project in two phases, starting the first phase from E-11 to Srinagar Highway. asserted
Authority → plan → Highway
Recently, CDA’s DWP approved PC-I worth Rs24.5 billion for the construction of the highway from Margalla Avenue to IJP Road. asserted
DWP → approve → Road
According to the PC-I, the 7.5km road, with three lanes on each side, will be completed within a year. uncertain
road → accord → year
Officials of the engineering wing said around 17 bridges and overpasses were part of the project. asserted
bridges → say → project
However, sources said that now CDA has decided to execute 11th Avenue in two phases. asserted
CDA → say → phases
In first priority phase, the 3.5km road will be constructed from E-11 interchange to Srinagar Highway, including an interchange at Srinagar Highway. asserted
road → construct → Highway
DWP recently approved PC-I worth Rs24.5 billion for construction of highway from Margalla Avenue to IJP Road “Recently, during a meeting it was decided that this project will be carried out in two phases. asserted
project → approve → phases
Hopefully, the project will be formally started within two months as currently we are working on pre-tendering process,” said an engineer of CDA. asserted
engineer → start → CDA
He said that when this phase will be completed, Srinagar Highway will be connected with Margalla Avenue and overall traffic load will be divided on both Margalla Road and Srinagar Highway. asserted
load → say → Road
To a query, the engineer said that overall PC-I worth Rs24.5 billion had been approved, so “I guess for this portion of 3.5km with an interchange roughly Rs11 to 12 billion will be earmarked. asserted
billion → say → interchange
This is a guesswork as proper working is in progress,” he said. asserted
he → say → progress
It is relevant to note here that Prime Minister Shehbaz Sharif, during his first stint, had laid the foundation stone of 11th Avenue in June 2023, but the project was not started. asserted
project → note → June
The avenue is supposed to start from IJP ll allRoad and after passing between I-10 and I-11, G-10, G-11, F-10 and F-11, culminate at the E-11 interchange. asserted
avenue → suppose → interchange
From E-11 to D-12, a portion of the road has already been completed and is known as Iran Avenue. asserted
portion → complete → Avenue
After the construction of 9th Avenue decades ago, the CDA could not construct any major road. uncertain
CDA → construct → road
Work on the construction of 10th Avenue was started in 2022, but after completion of around 50pc of the work, the project was halted last year. asserted
project → start → work
CDA officials told Dawn that besides focusing on 11th Avenue, the authority should also complete the stalled 10th Avenue project, as the structure of the incomplete road was deteriorating. asserted
structure → tell → road
They said 10th Avenue was a federally funded project and, due to the non-release of funds, it had been left abandoned. asserted
it → say → funds
The officials said the CDA had requested the federal government several times for release of fund, but to no avail. asserted
CDA → say → avail
According to the CDA, the total cost of the 10th Avenue project was Rs10.2 billion, but the government had released only around Rs4 billion. uncertain
government → accord → billion
That was why the project was halted, they said. asserted
they → halt → ?
They said that under the original plan, the project should have been completed by December 2024, but the federal government did not allocate any funds for the public welfare project in its 2024-25 and 2025-26 budgets. asserted
government → say → budgets
On the other hand, earthwork and structure from I.J.P to H-9 have been decaying and also causing inconvenience for public. asserted
earthwork → decay → public
The officials said with little funding, at least this portion could be brought under use with asphalt work. uncertain