Prime Minister Mark Carney on Friday listed the 800-kilometre Mackenzie Valley Highway as a project of national interest, the first project in Canada’s North to receive the status, which is meant to speed federal approvals.
asserted
which → list → approvals
Ottawa says the all-season road in the Northwest Territories will connect isolated communities, open up resources and strengthen Arctic security.
asserted
road → say → security
But the highway’s environmental assessment, under way since 2013, is not finished.
asserted
assessment → finish → 2013
And the $4.2-billion construction estimate officials gave reporters excludes new bridges and ongoing maintenance, CTV News reported.
asserted
News → give → bridges
The highway is the third project added to the Building Canada Act’s list.
asserted
highway → add → list
It follows the Pacific Link oil pipeline between Alberta and B.C. and the Roberts Bank Terminal 2 port expansion in Delta, B.C., both listed in October.
asserted
It → follow → October
Carney made the announcement in Yellowknife alongside N.W.T. Premier R.J. Simpson.
asserted
Carney → make → Simpson
Carney was born in Fort Smith, N.W.T., and said that during his first year, the only route out of the town was a winter road.
asserted
route → bear → town
“These connections bring strength,” he said.
asserted
he → bring → strength
According to the Prime Minister’s Office, the highway would improve transportation for more than 10,000 people.
uncertain
highway → accord → people
That includes about 1,900 Sahtu region residents of Tulita, Norman Wells and Fort Good Hope, who would have an all-season road for the first time.
asserted
who → include → time
Those communities are now reached only by air, river barge and winter road.
asserted
communities → reach → air
The government estimates the route would cut about 1,300 kilometres from the drive between Yellowknife and Inuvik, shortening it from roughly 38 hours to 23.
asserted
route → estimate → 23
It would also trim about 900 kilometres from the trip between Edmonton and Inuvik.
asserted
It → trim → Edmonton
Peak construction would require 3,000 workers.
asserted
construction → require → workers
Building could start as early as late 2027, and the current plan would see the road open in 2032.
uncertain
road → start → 2032
Simpson, whose government is the project’s primary proponent, said at the announcement that the road “will connect communities and lower the cost of living in one of Canada’s most expensive regions, with prices most Canadians couldn’t even dream of.”
asserted
Canadians → say → prices
He added: “Of course, the region is also home to world-class mineral and petroleum resources, and the highway is key to unlocking those.”
asserted
highway → add → those
Costs and bridges
The federal budget tabled earlier this month set aside $3.1 billion over five years for the highway.
asserted
budget → table → highway
It pledged that Ottawa would fully fund construction and certain maintenance costs.
asserted
Ottawa → pledge → construction
At a technical briefing before the announcement, officials could not say how much maintenance Ottawa would cover or for how long, according to CTV.
uncertain
Ottawa → say → CTV
In September, Ottawa also committed $405 million through the Arctic Infrastructure Fund, some of it toward bridges.
asserted
Ottawa → commit → bridges
A new Crown corporation for major projects, budgeted at $187 million over five years, will take on the highway as its first job.
asserted
corporation → budget → job
It is not clear when that entity will be operating.
asserted
entity → operate → ?
The government says the project requires new bridges over the Great Bear, Liard and Mackenzie rivers.
asserted
project → say → rivers
In a statement responding to the announcement, LKFN Chief Kele Antoine said that if the highway is truly in the national interest, permanent bridges “must be integral to that commitment,” CBC News reported.
asserted
News → respond → commitment
Both are slated for expansion under Ottawa’s $32-billion NORAD modernization plan.
asserted
Both → slat → plan
The government says a reliable road between them would make it easier to move Canadian Armed Forces personnel, equipment and supplies, and to build defence infrastructure in the North.
asserted
it → say → North
The highway is part of the northern plan Carney announced in March, which the government says includes more than $35 billion in federal investments.
asserted
government → announce → investments
What the designation does—and doesn’t—do
Listing a project under the Building Canada Act lets the Major Projects Office coordinate federal regulatory requirements and align departments’ decisions.
asserted
Office → list → decisions
The act was passed last year as part of Bill C-5.
asserted
act → pass → Bill
The listing does not replace the treaty-based assessment under the Mackenzie Valley Resource Management Act, which the Mackenzie Valley Environmental Impact Review Board is conducting.
asserted
Board → replace → which
Officials expect that review to wrap up by the end of 2027.
asserted
review → expect → 2027
Writing for The Hub, Alicia Planincic, director of policy and economics at the Business Council of Alberta, argued that designation changes the question Ottawa is answering.
asserted
Ottawa → write → question
Whether a project goes ahead is settled; what remains is the conditions it must meet.
asserted
it → go → ?
She was writing about the West Coast pipeline, which has since been listed.
asserted
which → write → pipeline
“All this to say, if Canada wants to see a pipeline built, and built quickly, the national designation under the original act is still likely to be the surest bet to get it done,” she wrote.
asserted
she → say → act
It aims to speed approvals for all projects, partly through a one-year review timeline.
asserted
It → aim → timeline
The bill, also known as C-39, passed second reading in October and is now in committee.
asserted
bill → know → committee
The Liberals hold a majority, and Carney said this week he will whip the vote.