The World Bank has slightly downgraded a $150 million education project in Punjab, apparently due to the non-mobilisation of technical assistance and the unavailability of baseline data, despite substantial progress against other targets.
asserted
Bank → downgrade → targets
In its public disclosure, the Washington-based multilateral downgraded the overall implementation progress from ‘satisfactory’ to ‘moderately satisfactory’.
asserted
multilateral → base → satisfactory
It kept unchanged the progress towards development of projects’ development objectives at ‘moderately satisfactory’.
asserted
It → keep → satisfactory
The overall risk rating was also kept unchanged at moderate.
asserted
rating → keep → ?
“The project has continued to make progress against its targets, including achievement of the financial targets for the previous fiscal year.
asserted
project → continue → year
Progress has been recorded across the performance-based conditions,” the bank said.
asserted
bank → record → conditions
Enrolment in public-private partnership schools has increased substantially from the project baseline, with the year-four target achieved ahead of schedule.
asserted
target → increase → schedule
In addition, 1,092 more schools now provide early childhood care and education that meets quality standards.
asserted
that → provide → standards
World Bank cites missing technical help and baseline data despite enrolment gains
On the other hand, classroom construction has yet to begin, although preparatory activities have progressed.
asserted
activities → cite → hand
“The formal restructuring of the project to reflect the government’s revised construction plan remains an important next step,” the bank said, adding that the technical assistance supporting several reform deliverables has not yet been mobilised.
asserted
assistance → reflect → deliverables
Baseline data for the project also remains unavailable and will be addressed during restructuring.
asserted
data → remain → restructuring
“Continued progress on these arrangements, alongside the commencement of classroom construction, will be important to sustain implementation and achieve the project’s intended results,” the bank warned.
asserted
bank → continue → results
The World Bank’s executive directors approved the $150m loan in June 2024, with a closing deadline of June 2029.
asserted
directors → approve → June
The loan aims to increase participation rates of girls and boys in pre-primary and primary grades and to enhance reading proficiency in primary grades in Punjab.
asserted
loan → aim → Punjab
The project “Getting Results: Access and Delivery of Quality Education Services in Punjab Project (GRADES)” was designed to improve learning outcomes, recover from learning losses during the Covid-19 pandemic, strengthen school management, and expand school participation.
asserted
project → get → participation
This should contribute to higher completion rates and more years of schooling, with improved learning for both girls and boys.
asserted
This → contribute → girls
The project is expected to directly benefit approximately five million children, 7,000 headteachers, 165,000 teachers, and more than 3,000 teacher mentors in public schools and Punjab Education Foundation schools.
asserted
project → expect → schools
Project documents reported that, as of June 2024, more than seven million children in Punjab were out of school.
asserted
children → report → school
The GRADES project was expected to help the Government of Punjab substantially reduce this number.
asserted
Government → expect → number
In parallel, the project aimed to improve foundational learning outcomes for boys and girls already in school.
asserted
project → aim → school
It planned to do so by scaling up and strengthening public-private partnerships, improving school readiness among young children, enhancing the quality and use of teaching and learning materials and assessments, and improving the learning environment in schools.
asserted
It → plan → schools