The Trump administration is keeping the J.H. Campbell coal plant in West Olive, Michigan, operational through February 12, 2027, despite a court ruling that initially struck down the order. Energy Secretary Chris Wright issued the order to the Midwest grid operator and Consumers Energy, stating that it prevents blackouts and ensures reliable electricity. The order was issued after the U.S. Court of Appeals for the D.C. Circuit struck down the initial emergency order on September 11, and the administration is appealing the decision. Additionally, similar orders for seven other power plants in six states are ending between November 20 and December 31, 2026.
Written by AI on 2026-11-22, from this article's own text only (the story summary below draws on all the coverage).

AI analysis

Story summary

The Trump administration has ordered the Midcontinent Independent System Operator to keep the J.H. Campbell coal plant in West Olive, Michigan operational until February 12, 2027. This decision comes after a court rejected the administration's initial order to keep the plant open. The Energy Department under Secretary Chris Wright issued a new directive on November 14, 2026, ensuring that the plant remains available to prevent potential blackouts. The order directs the grid operator to use economic dispatch, running the plant only when necessary to manage costs. Constellation Energy, the operator of the plant, stated it will keep Units 3 and 4 operational as long as the DOE 202 Orders remain in effect. The move aims to ensure affordable and reliable electricity access for American families and businesses, especially during winter months when energy demand is high.

Written for “Trump Admin Extends Michigan Coal Plant Life” on 2026-11-22, grounded in this article and the 0 other(s) covering the same event.

Compared with similar articles

Nothing to compare against. No article is close enough to this one for the pipeline to have linked or judged the pair.

Story

Trump Admin Extends Michigan Coal Plant Life
Politics · 1 article(s) covering the same event.
How this article was measured signals, leaning charts, publisher record, byline, topics and claims

Signals How these are calculated →

Claims extracted
59
sentences that state something as happening or true
Uncertain
10%
6 of 59 hedged ("reportedly", "may", "according to")
Leaning
withheld
no quote in the article backed the model's score
Publisher signals
92/100
The Daily Caller's corrections and hedging, across everything collected from it. Not a measure of accuracy.
Outlets on this story
1
Politics
Same framing elsewhere
1
articles that frame the event the way this one does
Analyzed 2026-11-22 · how these are computed

How this is being covered How these are calculated →

Article leaning vs. publisher reliability
Source leaning vs. consistency

Publisher

The Daily Caller · 394 article(s) · 0 correction(s) detected
No corrections detected for this publisher. That may mean careful reporting, or simply that nothing has been checked.

Who wrote this

Simon August
23 article(s) here · 1 carrying a prediction
Constellation said in a statement to the DCNF that it “will continue to keep Eddystone Units 3 and 4 operational for as long as the DOE 202 Orders remain in force.”
Heritage Foundation analysts say a future administration could use the permitting bill the Senate passed to pull approved pipeline permits over climate change.
The groups wrote that more such agreements “may be executed shortly.”
Consumer advocates in seven states want a regional grid operator to delay its December auction, saying it could stick households with the bill for data centers.
Maryland and Virginia residents could face some of the country’s highest electric bills in 2026 as power prices rise faster there than nationally.
Grid United is the line’s developer, but the loan would go to the Wyoming Intertie project, Ashley Kang, who works in external affairs and communications at the company, told the DCNF in a statement.
A grid operator covering much of the eastern U.S. proposed a plan that could help states make data centers pay for power line upgrades.
2026-11-18 · assertive framing · Data Centers Could Get Stuck Paying For Grid Upgrades
The State Corporation Commission opens its evidentiary hearing Tuesday on NextEra’s purchase of Dominion Energy, which the companies say would create “the world’s largest regulated electric utility business by market capitalization.”
Over the years spanning 2026 to 2047, the repeal would save the power sector $160 billion in compliance costs, the agency estimated in the final rule, which used a three percent discount rate.
The company’s website says that a 14 percent decrease, which also takes effect Jan. 1, will partially offset the hike.
Also by Simon August
Nothing else under this byline is closely related to this article, so these are simply their most recent.
All 23 articles by Simon August →

Topics

Constellation Consumers Energy Energy Michigan the Midcontinent Independent System Operator

Subjects

DCNF ORG · 3× Michigan ORG · 3× Americans NORP · 2× Campbell PERSON · 2× Constellation ORG · 2× PJM ORG · 2× Trump PERSON · 2× Wright PERSON · 2× the Energy Department ORG · 2× Energy ORG · 1×

Narrative

PJM applied for the order after the unit ran out of its allowed operating hours during a summer heat spell, the department said in a Nov. 18 release. “The Trump Administration is committed to keeping the lights on and ensuring American families and businesses have access to affordable, reliable, and secure power,” a department spokesperson said in a statement to the DCNF.
framing: assertive · carried by 1 article(s) · first seen 2026-11-22
Constellation said in a statement to the DCNF that it “will continue to keep Eddystone Units 3 and 4 operational for as long as the DOE 202 Orders remain in force.”

Claims (59 extracted, 6 hedged)

The Trump administration is keeping a Michigan coal plant available into winter while it asks an appeals court to revisit a ruling against it. asserted
it → keep → it
Energy Secretary Chris Wright ordered the Midcontinent Independent System Operator, which runs the Midwest grid, and Consumers Energy to have the J.H. Campbell plant, in West Olive, Michigan, available to run through Feb. 12, 2027, the Energy Department announced Nov. 14. asserted
Department → order → Feb.
Emergency orders for seven other power plants in six states end between Nov. 20 and Dec. 31, the department’s records show. asserted
records → end → Nov.
“Ensuring coal plants such as the Campbell Plant are available to operate has prevented blackouts and likely saved lives,” Wright said in the release. asserted
Wright → ensure → release
“Americans deserve access to affordable, reliable, and secure electricity regardless of whether the wind is blowing or the sun is shining.” asserted
sun → deserve → electricity
The order directs the grid operator to use economic dispatch, running Campbell only when the emergency requires it and keeping costs down, the department said. asserted
department → direct → costs
Midwest grid operator media relations adviser McKenzie Barbknecht said in a statement to the Daily Caller News Foundation that plants kept open under the orders “are dispatched like any other resource – through economic dispatch to meet system needs at the lowest cost. asserted
plants → say → cost
The grid operator “does not disclose unit specific generation information,” Barbknecht said. asserted
Barbknecht → disclose → information
It is the first Campbell order since Sept. 11, when the U.S. Court of Appeals for the D.C. Circuit struck down Wright’s original emergency order for the plant. asserted
Court → strike → plant
The department has asked the court to rehear the case, and that request is still pending, Utility Dive reported on Nov. 16. asserted
Dive → ask → Nov.
The court threw out only the first Campbell order and has not reviewed the orders that followed it, the American Public Power Association noted in October. asserted
Association → throw → October
(RELATED: Trump’s Energy Department Keeps Ordering Coal Plants To Stay Open After Losing In Court) asserted
Department → order → Court
The first of the other orders, for Units 3 and 4 at Constellation Energy’s Eddystone Generating Station in Pennsylvania, was scheduled to end Nov. 20. asserted
first → schedule → Pennsylvania
Orders for plants in Florida, Washington, Indiana and Colorado run out over the following five weeks. asserted
Orders → run → weeks
Constellation said in a statement to the DCNF that it “will continue to keep Eddystone Units 3 and 4 operational for as long as the DOE 202 Orders remain in force.” asserted
Orders → say → force
Since Aug. 23, 2026, both units ran Sept. 1-3, Unit 3 ran again Sept. 4 and Unit 4 ran Oct. 14. asserted
Unit → run → Aug.
Operating the two units cost about $4.9 million in the order’s first term, from May 31 to Aug. 28, 2025, and $5.1 million in its second, the company said. uncertain
company → operate → second
When it sought repayment from PJM Interconnection, which runs the mid-Atlantic grid, Constellation deducted the net revenue the units earned. asserted
units → seek → revenue
The department renewed its order for Unit 4 at Talen Energy’s Wagner Generating Station in Anne Arundel County, Maryland, on Nov. 17, the day the previous order ended, its website shows. asserted
website → renew → Nov.
The new order runs about six weeks, through Dec. 31, after two 90-day terms. asserted
order → run → terms
PJM applied for the order after the unit ran out of its allowed operating hours during a summer heat spell, the department said in a Nov. 18 release. “The Trump Administration is committed to keeping the lights on and ensuring American families and businesses have access to affordable, reliable, and secure power,” a department spokesperson said in a statement to the DCNF. asserted
spokesperson → apply → DCNF
“At the request of PJM, the Energy Department took decisive action to strengthen grid reliability and ensure Americans across the mid-Atlantic region have a dependable power grid that delivers electricity when they need it most,” the spokesperson added. asserted
spokesperson → take → it
Talen and the Michigan attorney general’s office did not respond to the DCNF’s requests for comment. asserted
Talen → respond → comment
Consumers expects to ask the Federal Energy Regulatory Commission to let it recover $303 million in costs under the orders through Sept. 30, “including amounts already requested,” after applying $344 million in revenue from the Midwest grid operator, the company said in its quarterly filing. asserted
company → expect → filing
Consumers spokesman Brian Wheeler said in a statement to the DCNF that the company would not “speculate on future costs.” asserted
company → say → costs
He said Consumers has asked federal regulators “to allow us to recover most of those costs for the first three 90-day periods from customers in 10 other Midwest states who benefited from that power.” asserted
who → say → power
“Those cases are pending. asserted
cases → pende → ?
We will submit additional cost recovery filings for costs incurred complying with all subsequent 90-day periods,” Wheeler said. asserted
Wheeler → submit → periods
The utility wants ratepayers in 11 states, from Michigan and Illinois to Montana and the Dakotas, to cover the plant’s costs, the Environmental Defense Fund said, according to Utility Dive. uncertain
Fund → want → Dive
Wheeler said the utility “will continue to follow the law and operate our Campbell plant,” Utility Dive reported. asserted
Dive → say → plant
“Consistent with these emergency orders, we will work to ensure that everyone who benefits from power from the Campbell plant across the Midwest pays their fair share. asserted
who → work → share
“Coal-fired power plants have become a political football. asserted
plants → fire → ?
Democrats want to shut them down, Republicans want to keep them running indefinitely, and the political pendulum keeps on swinging,” Travis Fisher, director of energy and environmental policy studies at the Cato Institute, said in a statement to the DCNF. asserted
Fisher → want → DCNF
“This is an irrational way to manage the electricity grid, and consumers are left dealing with the consequences. asserted
consumers → manage → consequences
The answer is to get politics out of electricity decisions, rather than forcing ratepayers to pay for Washington’s latest intervention,” Fisher added. asserted
Fisher → get → intervention
Jordan Nader, a resident senior fellow for energy and environment at the R Street Institute, said in a statement to the DCNF that the new order does not meet the guardrails his colleague Michael Giberson called for in May. uncertain
Giberson → say → May
Those guardrails “should be transparent, based on cost-benefit analysis, and demonstrate consideration of alternatives,” Nader said. asserted
Nader → base → alternatives
The Midwest grid operator should spread Campbell’s costs across its region when it calls on the plant, he said. asserted
he → spread → plant
“It would be improper to isolate the costs and allocate them only to Michigan,” he added. asserted
he → isolate → Michigan
The department still says the plant is needed. asserted